Event History

November 2007:   First Wind briefs BOS on proposed Windfarm Project

August 2008:  BOS interviews and retains Eaton Peabody for consulting and legal services on proposed windfarm project

August 2008 thru December 2008:  BOS holds work sessions with Eaton Peabody on Tax Increment Financing issues

October 1, 2008:  First Winds holds a community forum on the proposed wind project

January thru February 2009: BOS holds work sessions with Eaton Peabody on Tax Increment Financing issues.

January 27, 2009:  BOS sponsors a community forum on the proposed wind project.

March 23, 2009:  Oakfield Town Meeting passes town meeting articles designating a Tax Increment Finance District for the Windfarm project

April 6, 2009:  First Wind applies for State Permit

April 8, 2009:  BOS begins sorting out process of State Permit Application.

April 29, 2009:  DEP says First Wind Applicaton is complete, statutory 185 day review starts.

June 3, 2009:  BOS creates and appoints a Five Member Sub-Commitee to review various components of the Oakfield Windfarm Application.

June-August 2009:  Windfarm Review holds ten (10) meetings on sorting out the DEP Application submitted by First Wind.

September 4, 2009:  The Windfarm Review Committee approves Final Report and submits recommendations to Board of Selectmen.